The Ontario Energy Board (OEB) is commencing Phase 2 of a hearing on its own motion to consider various issues related to Ontario’s Uniform Transmission Rates (UTRs). These issues have been identified in the years since Ontario’s UTR framework was established in Hydro One’s first rate application proceeding in 2000, and implemented in 2002 following the opening of Ontario’s electricity market.
Phase 1 of the generic hearing commenced in 2021 under OEB file number EB-2021-0243 and focused on setting the Export Transmission Service Rate. Phase 1 concluded in 2023. The OEB is now commencing Phase 2 of the generic hearing to focus on the following UTR-related issues. The issues may be revised, and additional issues may be raised, based on input from transmitters, customers, and other stakeholders:
- Timing of UTR decisions
Overview of issue: Transmitter revenue requirements are recovered through UTRs which are charged to all wholesale market participants, including electricity distributors. The UTRs are usually established annually with an effective date of January 1, and are based on the revenue requirements of Ontario’s rate-regulated electricity transmitters. The timing of transmitter revenue requirement proceedings does not always allow for the annual UTR decision to be finalized in December for January 1. This can lead to forgone revenue, which must then be calculated and included when UTRs are updated. In addition, new transmitters are being added to UTRs when their assets come into service, and this does not always align with a January 1 UTR update.
- Number of decimal places for UTRs
Overview of issue: UTRs paid by transmission customers are calculated to two decimal places (unlike distribution rates, which are calculated to four decimal places).
- Prorating transmission charges for new connections to account for when the connection took place in the month
Overview of issue: Transmission customers are charged a monthly rate ($ per kW) for line connection billing demand and a monthly rate ($ per kW) for transformation connection billing demand. Line connection and transformation connection charges for newly connected transmission customers in their first month of connection are not revised upward or downward in proportion to when in the month the new connection was made.
- Charges caused by planned transmission outages
Overview of issue: In a month when a planned transmission outage occurs, a transmission customer that transfers its load to another of its delivery points is charged more than it would be if the outage did not occur. This is because transmission charges are based on the monthly peak at each delivery point.
- Basis for Billing Renewable, Non-renewable and Energy Storage Facilities for Transmission
Overview of issue: The UTR establishes a gross load billing threshold of greater than 1 MW for non-renewable generating units and greater than 2 MW for renewable generating units for the transformation and connection rate pools paid for by transmission customers. The scope of this issue is to review whether the 1 MW and 2 MW thresholds are still the appropriate thresholds. The scope also includes considering the appropriate billing threshold for energy storage facilities. The scope of this issue does not include billing for distribution or whether energy storage facilities should be considered renewable or non-renewable (or something else) for purposes of gross load billing. The scope of this issue has been revised by the OEB from how it was first described in the October 15, 2021 Notice of Hearing for Phase 1 of the generic hearing on UTR-related issues.
- Gross load billing thresholds for renewable and non-renewable generation
Overview of issue: Beyond the question of appropriate gross load billing thresholds, set out in issue 5, there has been some uncertainty around the application of those thresholds to transmission customers – for example, with respect to incremental capacity resulting from a generator refurbishment. Clarification is currently provided to customers through OEB guidance.
The October 15, 2021 Notice of Hearing for Phase 1 outlined eight UTR-related issues. One of those, “setting the export transmission service (ETS) rate”, was the subject of Phase 1 and is concluded. In addition, the OEB will defer consideration of one issue – “calculation of network charge determinant” – to another time. Phase 2 of the generic hearing will focus on the six issues outlined above.
More information
Details and Updates
The OEB has issued a Decision and Order on a Generic Hearing on Uniform Transmission Rates-Related Issues and the Export Transmission Service Rate.
Submit a letter of comment
You can submit a letter of comment that will be considered by the panel deciding the application. Unless the notice states otherwise, your letter of comment will be accepted until the record of the proceeding is closed (which usually occurs with the filing of the applicant’s final reply argument). However, you are encouraged to submit your letter as early in the process as you can. Depending on timing of receipt of letters of comment, the applicant will typically provide a respond to the issues raised in those letters. Your letter will be provided directly to the panel of Commissioners who will be deciding whether the application is approved. The panel will consider your comments in reaching their decision. The panel will only be able to consider comments which relate to issues which are within the authority of the OEB and relevant to the issues being considered by the panel.
More about commenting and privacy
All letters of comment sent to the OEB are placed on the public record. This means the letters will be placed on our website. Before the letter of comment is placed on the public record, personal contact information contained in the address, phone number, and email address fields of this form is removed. The individual's name and the content of the letter will become part of the public record.
If you would like a response from the applicant, please send a copy of your letter directly to the applicant, including your personal contact information. The OEB removes your personal contact information from your letter for privacy reasons before it is posted to our website.