Hydro One Networks Inc. - Waasigan Expropriation

Hydro One Networks Inc.
EB-2024-0319

Hydro One Networks Inc. (Hydro One) is asking the Ontario Energy Board (OEB) for permission to expropriate interests in certain lands between the Municipality of Shuniah and the Town of Atikokan in Ontario, to construct and operate a new 230 kilovolt double-circuit transmission line between Lakehead Transformer Station (TS) and Mackenzie TS (Project). 

The Project comprises two phases. Phase 1 consists of constructing a new 230 kilovolt (kV) double-circuit transmission line that spans approximately 190 km to connect the existing Lakehead TS with the existing Mackenzie TS. Phase 2 consists of constructing a new 230 kV single-circuit transmission line spanning approximately 170 km from the existing Mackenzie TS to the existing Dryden TS. The anticipated in-service date for Phase 1 is December 2025, while Phase 2 is expected to be in-service by December 2027. 

Under a separate Decision and Order dated April 16, 2024, the Ontario Energy Board granted Hydro One leave to construct and operate the Project. 

Phase 1 of the Project will require Hydro One to acquire land rights from approximately 136 directly impacted property owners. Hydro One is not requesting permission to expropriate interests in lands related to Phase 2 at this time.

Hydro One’s application is about the expropriation of certain specific lands only. It is not about compensation. The OEB will consider the public interest when making any order authorizing Hydro One to expropriate land. The OEB does not have the authority to determine the amount of compensation payable. If the OEB authorizes Hydro One to expropriate and the parties do not agree upon compensation, then the compensation must be determined under the Expropriations Act or by the Ontario Land Tribunal.

Type: Expropriation

This application will be heard using the LTC Complex electricity & Natural Gas performance standard (pdf).

Find out more about OEB Performance Standards for Processing Applications and use the Application Planning Tool to assist you with an estimate of the milestones in this proceeding.

See the application notice 
See the application 
See all documents related to this application 
The above links will take you to our document repository

Participate

There are three ways to participate in the OEB hearing process: as an Intervenor, submitting a Letter of Comment or to Follow a Proceeding.

This table illustrates the different levels of participation. Find out more about participating in an OEB hearing, including becoming an intervenor.

Participation ActivitiesIntervenorLetter of CommentFollow a Proceeding
Receive OEB-issued documents by email
Submit a Letter of Comment
Listen to live broadcast of the oral hearing
Participate in oral hearing
Present Evidence
Respond to questions about evidence
Ask other parties to the proceeding questions
Provide argument

Submit a letter of comment

You can submit a letter of comment that will be considered by the panel deciding the application. Unless the notice states otherwise, your letter of comment will be accepted until the record of the proceeding is closed (which usually occurs with the filing of the applicant’s final reply argument). However, you are encouraged to submit your letter as early in the process as you can. Depending on timing of receipt of letters of comment, the applicant will typically provide a respond to the issues raised in those letters. Your letter will be provided directly to the panel of Commissioners who will be deciding whether the application is approved. The panel will consider your comments in reaching their decision. The panel will only be able to consider comments which relate to issues which are within the authority of the OEB and relevant to the issues being considered by the panel.

More about commenting and privacy
All letters of comment sent to the OEB are placed on the public record. This means the letters will be placed on our website. Before the letter of comment is placed on the public record, personal contact information contained in the address, phone number, and email address fields of this form is removed. The individual's name and the content of the letter will become part of the public record.

If you would like a response from the applicant, please send a copy of your letter directly to the applicant, including your personal contact information. The OEB removes your personal contact information from your letter for privacy reasons before it is posted to our website.

Add Your Letter of Comment

All information provided in this field will be made publicly available and placed on the OEB website. Please do not include any personal contact information in this section.
Upload an attachment only if you need to submit additional information relating to your comment. Only PDF and Word files will be accepted. All information provided in the document you attach will be made publicly available and placed on the OEB website. Please do not include any personal contact information in your attached document.
Choose file
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Get updates about this application:

CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Or mail the below address with the reference number EB-2024-0319

Ontario Energy Board
P.O. Box 2319
2300 Yonge Street, 27th Floor
Toronto ON M4P 1E4
Attn: Registrar