The Ontario Energy Board proposed amendments to the Distribution System Code to provide additional time for applicants of large embedded generation facilities that require transmission upgrades to sign a connection cost agreement with the distributor for the facility and maintain its capacity allocation.

Updates
Updates
Date Issue / Document
November 14, 2012

The Board has released a Notice of Amendment to the Distribution System Code. The amendments, set out in the Board’s Notice of Amendment to a Code, come into force today.

The following written comments were received on the Board’s Notice of Revised Proposed Amendments to the Distribution System Code dated October 11, 2012:

October 11, 2012

The Board has issued revised proposed amendments to the Distribution System Code regarding timelines to develop connection cost agreements for large embedded generation facilities.

The following written comments were received on the Board’s Notice of Proposed Amendments to the Distribution System Code dated July 27, 2012:

July 27, 2012

The Board has issued proposed amendments to the Distribution System Code regarding timelines to develop connection cost agreements for large embedded generation facilities.