Hydro One Networks Inc.

Current applications before the Board

Title: Hydro One Networks Inc. (EB-2024-0142) - Port Colborne Expropriation

Case number: EB-2024-0142

Type:

Filed: April 11, 2025

Hydro One Networks Inc. (Hydro One) is asking the Ontario Energy Board (OEB) for permission to expropriate interests in certain lands near the City of Port Colborne. Hydro One says that the expropriation is needed so that it may continue to operate and maintain existing transmission lines that are located on the lands. The existing transmission lines were originally constructed in the 1960s and form part of the Independent Electricity System Operator controlled transmission grid.

Hydro One’s application is about the expropriation of certain lands only. It is not about compensation. The OEB will consider the public interest when making any order authorizing Hydro One to expropriate land. The OEB does not have the authority to determine the amount of compensation payable. If the OEB authorizes Hydro One to expropriate and the parties do not agree upon compensation, then the compensation must be determined under the Expropriations Act by the Ontario Land Tribunal.

Type: Expropriation

This application will be heard using the LTC Complex electricity & Natural Gas performance standard (pdf).

Find out more about OEB Performance Standards for Processing Applications and use the Application Planning Tool to assist you with an estimate of the milestones in this proceeding.

See the application notice 
See the application 
See all documents related to this application 
The above links will take you to our document repository

Participate

There are three ways to participate in the OEB hearing process: as an Intervenor, submitting a Letter of Comment or to Follow a Proceeding.

This table illustrates the different levels of participation. Find out more about participating in an OEB hearing, including becoming an intervenor.

Participation ActivitiesIntervenorLetter of CommentFollow a Proceeding
Receive OEB-issued documents by email
Submit a Letter of Comment
Listen to live broadcast of the oral hearing
Participate in oral hearing
Present Evidence
Respond to questions about evidence
Ask other parties to the proceeding questions
Provide argument

See application details and how to participate

Title: Hydro One Networks Inc. - Waasigan Expropriation

Case number: EB-2024-0319

Type:

Filed: January 09, 2025

Hydro One Networks Inc. (Hydro One) is asking the Ontario Energy Board (OEB) for permission to expropriate interests in certain lands between the Municipality of Shuniah and the Town of Atikokan in Ontario, to construct and operate a new 230 kilovolt double-circuit transmission line between Lakehead Transformer Station (TS) and Mackenzie TS (Project). 

The Project comprises two phases. Phase 1 consists of constructing a new 230 kilovolt (kV) double-circuit transmission line that spans approximately 190 km to connect the existing Lakehead TS with the existing Mackenzie TS. Phase 2 consists of constructing a new 230 kV single-circuit transmission line spanning approximately 170 km from the existing Mackenzie TS to the existing Dryden TS. The anticipated in-service date for Phase 1 is December 2025, while Phase 2 is expected to be in-service by December 2027. 

Under a separate Decision and Order dated April 16, 2024, the Ontario Energy Board granted Hydro One leave to construct and operate the Project. 

Phase 1 of the Project will require Hydro One to acquire land rights from approximately 136 directly impacted property owners. Hydro One is not requesting permission to expropriate interests in lands related to Phase 2 at this time.

Hydro One’s application is about the expropriation of certain specific lands only. It is not about compensation. The OEB will consider the public interest when making any order authorizing Hydro One to expropriate land. The OEB does not have the authority to determine the amount of compensation payable. If the OEB authorizes Hydro One to expropriate and the parties do not agree upon compensation, then the compensation must be determined under the Expropriations Act or by the Ontario Land Tribunal.

Type: Expropriation

This application will be heard using the LTC Complex electricity & Natural Gas performance standard (pdf).

Find out more about OEB Performance Standards for Processing Applications and use the Application Planning Tool to assist you with an estimate of the milestones in this proceeding.

See the application notice 
See the application 
See all documents related to this application 
The above links will take you to our document repository

Participate

There are three ways to participate in the OEB hearing process: as an Intervenor, submitting a Letter of Comment or to Follow a Proceeding.

This table illustrates the different levels of participation. Find out more about participating in an OEB hearing, including becoming an intervenor.

Participation ActivitiesIntervenorLetter of CommentFollow a Proceeding
Receive OEB-issued documents by email
Submit a Letter of Comment
Listen to live broadcast of the oral hearing
Participate in oral hearing
Present Evidence
Respond to questions about evidence
Ask other parties to the proceeding questions
Provide argument

See application details and how to participate

Contact this Utility:

483 Bay Street
7th Floor, South Tower
Toronto ON M5G 2P5
1,458,062
Number of customers
961,301 sq. km
Total size of service area
124,948 km
Total km of electricity line

The electricity utility scorecards measure how well Ontario's electricity utilities are performing each year. It is designed to encourage utilities to operate effectively, continually seek ways to improve productivity and focus on improvements that their customers value. Utilities report their scorecard performance results annually, and make the results available to the public. 

The scorecard can be used as a tool for consumers to assess for themselves the value of the service received from their electricity utility. For example: 

  • When service appointments are booked with my utility, how often did they show up on time?
  • How often did my power go out, and how long did the utility take to fix the problem and restore power? 
  • How successful is my utility at issuing accurate bills? 
  • Did my utility answer phone calls from customers in a timely way?

Use our report generator tool to compare costs and performance between distributors

New residential/small business services connected on time
99.97% (2023)

The utility must connect new service for the customer within five business days, 90 % of the time, unless the customer agrees to a later date. This timeline depends on the customer meeting specific requirements ahead of time (such as no electrical safety concerns in the building, customer's payment information complete, etc.)

Target met
OEB Target = 90%
2013 97.4%
2014 97.4%
2015 97.5%
2016 98.6%
2017 98.06%
2018 99.32%
2019 99.81%
2020 99.78%
2021 99.98%
2022 99.86%
2023 99.97%

Scheduled appointments met on time
100% (2023)

For appointments during the utility's regular business hours, the utility must offer a window of time that is not more than four hours long, and must arrive within  that window, 90 % of the time. 

Target met
OEB Target = 90%
2013 98.4%
2014 99.3%
2015 98.5%
2016 99.5%
2017 98.94%
2018 99.95%
2019 100%
2020 99.98%
2021 100%
2022 99.99%
2023 100%

Telephone calls answered on time
78.24% (2023)

During regular call centre hours, the utility's call centre staff must answer within 30 seconds of receiving the call directly or having the call transferred to them, 65 % of the time

Target met
OEB Target = 65%
2013 63.9%
2014 69.6%
2015 76.4%
2016 74.2%
2017 81.85%
2018 78.05%
2019 76.83%
2020 70.18%
2021 70.41%
2022 72.65%
2023 78.24%

Billing accuracy
99.04% (2023)

An important part of business is ensuring that customer's bills are accurate. The utility must report on its success at issuing accurate bills to its customers.

More information about billing accuracy

Target met
OEB Target = 98%
2014 94.63%
2015 98.59%
2016 99.04%
2017 99.28%
2018 99%
2019 99%
2020 99.35%
2021 99.17%
2022 99.01%
2023 99.04%

Complaints
0.06 (2023)

This metric measures the number of complaints the Ontario Energy Board received from customers about matters within our authority. Complaints made directly to the utility are not reported here. We measure this per 1000 customers so utilities that serve much larger or smaller populations can be compared against each other. 

Year Complaints per 1000 customers Total number of complaints
2013 0.53 647
2014 0.49 593
2015 0.34 425
2016 0.30 397
2017 0.10 127
2018 0.07 87
2019 0.07 99
2020 0.04 55
2021 0.05 77
2022 0.07 100
2023 0.06 85

Average number of hours power to a customer was interrupted
7.50421h (2023)

An important feature of a reliable distribution system is recovering from power outages as quickly as possible. The utility must track the average length of time, in hours, that its customers have experienced a power outage over the past year. 

2013 26.57h
2014 9.42h
2015 12.22h
2016 7.83275h
2017 7.94892h
2018 6.81642h
2019 7.03707h
2020 7.26737h
2021 6.49996h
2022 6.94832h
2023 7.50421h

Average number of times power to a customer was interrupted
2.82113 (2023)

Another important feature of a reliable distribution system is reducing the frequency of  power outages. Utilities must also track the number of times their customers experienced a power outage during the past year.

More information about interruption frequency

2013 4.23
2014 2.96
2015 3.07
2016 2.47338
2017 2.31972
2018 2.21006
2019 2.49931
2020 2.53943
2021 2.35941
2022 2.51272
2023 2.82113

Efficiency rating
4 (2023)

The utility must manage its costs successfully in order to help assure its customers they are receiving value for the cost of the service they receive. Utilities' total costs are evaluated to produce a single efficiency ranking. This is divided into five groups based on how big the difference is between each utility's actual and predicted costs. Distributors whose actual costs are lower than their predicted costs are considered more efficient.

  • 1 = Actual costs are 25% or more below predicted costs
  • 2 = Actual costs are 10% to 25% below predicted costs
  • 3 = Actual costs are within +/- 10% of predicted costs
  • 4 = Actual costs are 10% to 25% above predicted costs
  • 5 = Actual costs are 25% or more above predicted costs
2013 5
2014 5
2015 5
2016 4
2017 4
2018 4
2019 4
2020 4
2021 4
2022 4
2023 4

Cost per customer
$1,369 (2023)

A simple measure that can be used as a comparison with other utilities is the utility's total cost per customer. 

Total cost is a sum of all the costs incurred by the utility to provide service to its customers. The amount is then divided by the utility's total number of customers. This amount does not represent how much customers pay for their utility services.

More information about Cost per Customer

2013 $1,046
2014 $1,069
2015 $983
2016 $987
2017 $974
2018 $1,022
2019 $1,051
2020 $1,024
2021 $1,033
2022 $1,172
2023 $1,369